norventusForgeToolkits for your Work
PremiumConstruction · Earthworks

Compaction lifts and roller time

Number of lifts, roller passes and hours to compact a fill area.

Get this tool with its role plan

This is a premium tool. It comes with its role's plan: sign in, then add the role in Billing.

Comes with the equipment operator plan: every tool for the role, from $10.20 a month at the launch price.

  • Your own numbers, worked out as often as you like
  • The full fill qa plan you can print or save to My work
  • 5 cited sources, linked, with the checks to make
  • Every other tool for the same role, in the same plan
  • A plain-words read of your result (a fuller AI read with the Bifrost AI add-on)

Included in these role plans

Equipment operatorForeman and site leadLaborerCivil engineer

Example result · fictional numbers

What you get: fill qa plan

Worked out by this tool from its default inputs. Its role plan lets you run your own numbers, print the sheet and save it.

5 lifts to 114.0 lb per cu ft dry (95% of standard Proctor), 40 density tests, 18.6 h of rolling at $2,237.76

Lifts
5
Coverage per hour
10,725 sq ft per lift
Roller hours
18.6 h (2.1 days at 9 h)
Compacted volume
4,444 CY

Density target and moisture

Density spec
95% of standard Proctor (ASTM D698)
Field dry density to pass
114.0 lb per cu ft or more (95% of 120.0)
Optimum moisture
12.0%; the fill is at 9.0%
Water per lift
It is 3.0 points dry of optimum: add about 9,842 gal a lift, plus what evaporates
Water for the whole fill
49,209 gal over 5 lifts

Also on the sheet

  • Lift schedule · 4 lines, starting with “Lifts”
  • Testing plan · 4 lines, starting with “Tests per lift”
  • Roller cost and what if · 5 lines, starting with “Roller cost”

The plain-words read of this example

The fill goes in 5 lifts of about 7.2 in, and each must reach 114.0 lb per cu ft dry, 95% of the 120.0 Proctor maximum. It is 3.0 points dry of optimum: add about 9,842 gal a lift, plus what evaporates. Plan 40 density tests, 8 a lift. Rolling takes 18.6 h with 6 passes, about 2.1 days, and costs $2,237.76. Prove the passes on a test strip before you commit the schedule.

5 cited sources

  • ASTM D698, Laboratory Compaction Characteristics of Soil Using Standard Effort (ASTM International)
  • ASTM D1557, Laboratory Compaction Characteristics of Soil Using Modified Effort (ASTM International)
  • ASTM D6938, In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (ASTM International)
  • 29 CFR 1926.602, Material handling equipment (earthmoving and compacting equipment) (OSHA)
  • Caterpillar Performance Handbook (edition 49) (Caterpillar, via MacAllister Machinery (Cat dealer))

Plus 5 step-by-step checks, a print layout and a link that reopens it with your numbers.

Sign in to pin this tool to My work.

Norventus

Applied Intelligence, three ways.

One way of thinking, built for three different jobs. Here is how they compare.

  • Applied Intelligence

    Watch TowerFor Business

    Who it is for
    Leaders and operators of an organization.
    What you get
    Your team, goals and KPIs, assets on one map and a work tracker, set up with you in the Watch Tower Console in four weeks, then reviewed with you every week.
    How to start
    Start from your goal. The demo is free.
    Visit Watch Tower
  • Applied Intelligence

    BeaconFor Professionals

    Who it is for
    One professional and where their career goes next.
    What you get
    A personal career console: news for your role, certifications, a pay-target planner, lessons and projects.
    How to start
    3 days free. No card needed to start.
    Visit Beacon
  • Applied Intelligence

    ForgeFor your Work

    Who it is for
    The people who do the work, on site (Crew) or at a desk (Labs).
    What you get
    Small, clear tools for everyday jobs: calculators, quick references and checklists.
    How to start
    Many tools are free. No account needed.
    You are here