Pipe bedding and backfill volume

Bedding and pipe-zone stone, final backfill and spoil for a pipe trench.

Get this tool with its role plan

This is a premium tool. It comes with its role's plan: sign in, then add the role in Billing.

Comes with the estimator plan: every tool for the role, from $10.20 a month at the launch price.

  • Your own numbers, worked out as often as you like
  • The full pipe trench sheet you can print or save to My work
  • 4 cited sources, linked, with the checks to make
  • Every other tool for the same role, in the same plan
  • A plain-words read of your result (a fuller AI read with the Bifrost AI add-on)

Included in these role plans

PlumberForeman and site leadCivil engineerEstimator

Example result · fictional numbers

What you get: pipe trench sheet

Worked out by this tool from its default inputs. Its role plan lets you run your own numbers, print the sheet and save it.

140 tons of stone, 8 loads of spoil out, $4,893.23 for 400 ft ($12.23 a foot) over 3 days

Excavation
356 bank CY
Bedding and pipe-zone stone
100 CY → 140 tons
Final backfill (compacted)
243 CY
Pipe displacement
13 CY
Surplus spoil (bank)
113 CY before shrink

Order list

Bedding and pipe-zone stone
140.5 tons (100 CY at 1.40 tons per CY)
Pipe zone depth
30.5 in: 6.0 in bedding, 12.5 in pipe, 12.0 in over the crown
Side clearance
11.8 in each side of the pipe in a 3.0 ft trench, for haunching and compaction
Imported fill (only if short)
None needed
Spoil trucks out
8 loads

Also on the sheet

  • Earthwork balance · 3 lines, starting with “Dug from the trench”
  • Cost sheet · 5 lines, starting with “Stone”
  • Daily schedule · 4 lines, starting with “Working days”

The plain-words read of this example

This 400 ft run needs 140 tons of bedding and pipe-zone stone and 243 CY of compacted final backfill. At 25% swell and 10% shrink the native spoil leaves 108 CY loose to haul off (8 loads). Reusing the spoil costs $4,893.23 and importing select fill costs $13,838.05; your plan to reuse the native spoil is $12.23 a foot. At 160 ft a day it takes 3 working days. The embedment class and compaction come from your project spec and ASTM D2321.

4 cited sources

  • ASTM D2321, Standard Practice for Underground Installation of Thermoplastic Pipe for Sewers and Other Gravity-Flow Applications (ASTM International)
  • Installation Guide for Solid Wall PVC Sewer Pipe (Uni-Bell PVC Pipe Association)
  • Swell and void percentage, load factors (Caterpillar)
  • 29 CFR 1926.651, Specific excavation requirements (OSHA)

Plus 5 step-by-step checks, a print layout and a link that reopens it with your numbers.

Sign in to pin this tool to My work.

Norventus

Applied Intelligence, three ways.

One way of thinking, built for three different jobs. Here is how they compare.

  • Applied Intelligence

    Watch TowerFor Business

    Who it is for
    Leaders and operators of an organization.
    What you get
    Your team, goals and KPIs, assets on one map and a work tracker, set up with you in the Watch Tower Console in four weeks, then reviewed with you every week.
    How to start
    Start from your goal. The demo is free.
    Visit Watch Tower
  • Applied Intelligence

    BeaconFor Professionals

    Who it is for
    One professional and where their career goes next.
    What you get
    A personal career console: news for your role, certifications, a pay-target planner, lessons and projects.
    How to start
    3 days free. No card needed to start.
    Visit Beacon
  • Applied Intelligence

    ForgeFor your Work

    Who it is for
    The people who do the work, on site (Crew) or at a desk (Labs).
    What you get
    Small, clear tools for everyday jobs: calculators, quick references and checklists.
    How to start
    Many tools are free. No account needed.
    You are here