PremiumConstruction · Paving

Asphalt paving tonnage

Hot-mix tons, truck loads and tack coat for a paving area and thickness.

Get this tool with its role plan

This is a premium tool. It comes with its role's plan: sign in, then add the role in Billing.

Comes with the civil engineer plan: every tool for the role, from $10.20 a month at the launch price.

  • Your own numbers, worked out as often as you like
  • The full paving plan you can print or save to My work
  • 3 cited sources, linked, with the checks to make
  • Every other tool for the same role, in the same plan
  • A plain-words read of your result (a fuller AI read with the Bifrost AI add-on)

Included in these role plans

Foreman and site leadTruck driverCivil engineerProject managerEstimator

Example result · fictional numbers

What you get: paving plan

Worked out by this tool from its default inputs. Its role plan lets you run your own numbers, print the sheet and save it.

90.6 tons in 5 loads, 2 passes at 16.5 ft a minute, 5 trucks on a 65-minute cycle, $8,750.39

Area
800 sq yd
Hot-mix asphalt
90.6 tons
Truck loads
5
Tack coat
40 gal

Paving plan

Passes across the width
2 passes of 12.0 ft for 24.0 ft; 1 longitudinal joint
Paver travel
600 ft in all (2 passes of 300 ft)
Mix per foot of travel
302 lb (12.0 ft wide, 2.00 in, 110 lb per sq yd per in, plus waste)
Paver speed to match
16.5 ft a minute at 150 tons an hour
Yield check
each 20.0-ton load should cover about 132 ft of a 12.0 ft pass

Also on the sheet

  • Trucks and schedule · 5 lines, starting with “Truck cycle”
  • Cost sheet · 5 lines, starting with “Hot mix”

The plain-words read of this example

The job takes 90.6 tons of hot mix in 5 loads, laid in 2 passes of 12.0 ft. At 150 tons an hour the paver runs about 16.5 ft a minute and paving takes 36 min, so plan 1 day. A 65-minute truck cycle needs 5 trucks to keep the paver moving. Each load should cover about 132 ft of a pass; check it every load. Mix, tack and trucking come to $8,750.39, or $10.94 a square yard.

3 cited sources

  • Longitudinal Joint Construction and Density, Tech Brief FHWA-HIF-21-023 (Federal Highway Administration, Asphalt Pavement Technology Program)
  • Asphalt Paving Handbook, 7.6 Establishing Paver Speed (National Asphalt Pavement Association (AAPTP handbook))
  • Asphalt Paving Handbook, 7.5 Layer Thickness (rolldown and spread rate) (National Asphalt Pavement Association (AAPTP handbook))

Plus 5 step-by-step checks, a print layout and a link that reopens it with your numbers.

Sign in to pin this tool to My work.

Norventus

Applied Intelligence, three ways.

One way of thinking, built for three different jobs. Here is how they compare.

  • Applied Intelligence

    Watch TowerFor Business

    Who it is for
    Leaders and operators of an organization.
    What you get
    Your team, goals and KPIs, assets on one map and a work tracker, set up with you in the Watch Tower Console in four weeks, then reviewed with you every week.
    How to start
    Start from your goal. The demo is free.
    Visit Watch Tower
  • Applied Intelligence

    BeaconFor Professionals

    Who it is for
    One professional and where their career goes next.
    What you get
    A personal career console: news for your role, certifications, a pay-target planner, lessons and projects.
    How to start
    3 days free. No card needed to start.
    Visit Beacon
  • Applied Intelligence

    ForgeFor your Work

    Who it is for
    The people who do the work, on site (Crew) or at a desk (Labs).
    What you get
    Small, clear tools for everyday jobs: calculators, quick references and checklists.
    How to start
    Many tools are free. No account needed.
    You are here