Schedule float and critical path (simple)

For up to three parallel task chains to a milestone: which chain is critical, the float on the others and the slack to the deadline.

Get this tool with its role plan

This is a premium tool. It comes with its role's plan: sign in, then add the role in Billing.

Comes with the civil engineer plan: every tool for the role, from $10.20 a month at the launch price.

  • Your own numbers, worked out as often as you like
  • The full schedule sheet you can print or save to My work
  • 5 cited sources, linked, with the checks to make
  • Every other tool for the same role, in the same plan
  • A plain-words read of your result (a fuller AI read with the Bifrost AI add-on)

Included in these role plans

Foreman and site leadCivil engineerProject manager

Example result · fictional numbers

What you get: schedule sheet

Worked out by this tool from its default inputs. Its role plan lets you run your own numbers, print the sheet and save it.

Path A is critical: finishes Nov 23, 2026 (Nov 30, 2026 with weather), milestone Nov 27, 2026

Critical path
Path A: 26 days
Path B total float
4 days (length 22)
Path C total float
10 days (length 16)
Project float to milestone
4 days spare

Milestone dates

Start
Oct 17, 2026; first working day Oct 19, 2026, working 5 days a week
Critical path (Path A) finishes
Nov 23, 2026 after 26 working days
With the weather allowance
Nov 30, 2026 (5 working days added)
Contract milestone
Nov 27, 2026 (30 working days from the start)
Float to the milestone
4 working days; after weather 1 working day short
Verdict
Tight: the critical path fits, but the weather allowance would make it 1 working day late

Also on the sheet

  • Paths and critical tasks · 7 lines, starting with “Path A”
  • What if Path B slips 6 working days · 3 lines, starting with “Float that absorbs it”
  • Cost of finishing late · 4 lines, starting with “Liquidated damages”

The plain-words read of this example

Path A is the critical path at 26 working days: starting Oct 17, 2026 it finishes Nov 23, 2026, against a milestone of Nov 27, 2026. Tight: the critical path fits, but the weather allowance would make it 1 working day late. If Path B slips 6 working days, its float absorbs 4 working days and the critical path moves 2 working days, leaving the job 5 calendar days late. That costs $7,500.00 in liquidated damages, charged per calendar day, plus $6,600.00 in general conditions. Crash it: $9,000.00 to gain 3 working days against $14,100.00 in damages and general conditions. Give written notice of any excusable delay within 10 days.

5 cited sources

  • FAR 52.211-12, Liquidated Damages: Construction (Acquisition.gov (Federal Acquisition Regulation))
  • FAR 52.236-15, Schedules for Construction Contracts (Acquisition.gov (Federal Acquisition Regulation))
  • FAR 52.249-10, Default (Fixed-Price Construction) (Acquisition.gov (Federal Acquisition Regulation))
  • Climate Data Online (NOAA National Centers for Environmental Information)
  • AACE International Recommended Practices (29R-03 Forensic Schedule Analysis, 52R-06 Time Impact Analysis) (AACE International)

Plus 5 step-by-step checks, a print layout and a link that reopens it with your numbers.

Sign in to pin this tool to My work.

Norventus

Applied Intelligence, three ways.

One way of thinking, built for three different jobs. Here is how they compare.

  • Applied Intelligence

    Watch TowerFor Business

    Who it is for
    Leaders and operators of an organization.
    What you get
    Your team, goals and KPIs, assets on one map and a work tracker, set up with you in the Watch Tower Console in four weeks, then reviewed with you every week.
    How to start
    Start from your goal. The demo is free.
    Visit Watch Tower
  • Applied Intelligence

    BeaconFor Professionals

    Who it is for
    One professional and where their career goes next.
    What you get
    A personal career console: news for your role, certifications, a pay-target planner, lessons and projects.
    How to start
    3 days free. No card needed to start.
    Visit Beacon
  • Applied Intelligence

    ForgeFor your Work

    Who it is for
    The people who do the work, on site (Crew) or at a desk (Labs).
    What you get
    Small, clear tools for everyday jobs: calculators, quick references and checklists.
    How to start
    Many tools are free. No account needed.
    You are here